Chinese tunnelling contractor claims new record on Georgia highway tunnel drive

Premium Content
The Caucasus TBM has bored the 8,860m-long Gudauri Tunnel for the KK Highway in Georgia The Caucasus TBM has bored the 8,860m-long Gudauri Tunnel for the KK Highway in Georgia (Image: China Railway Tunnel Group)

China Railway Tunnel Group has claimed what it said was a new record tunnel boring machine tunnelling (TBM) during the construction of a tunnel on a major new highway in Georgia.

The company said that it had achieved a maximum monthly advance of 426 metres on the Gudauri Tunnel on Georgia’s North-South KK Highway.

That was a record in large-diameter TBM tunnel construction, surpassing the previously recognized industry maximum of 320 metres per month, it claimed.

It used the Caucasus TBM for the project, which is 182 metres in length and weighs 3,900 tons. It has a maximum thrust of 22.600 tones and total power of 9,900 kilowatts. The company claimed that with an excavation diameter of 15.08 metres, it is one of the largest of its kind.

The two-way, dual carriageway KK Highway is 22.7km long and the 10km lot 1 section, which includes the 8,860m-long Gudauri Tunnel, is being built by China Railway Tunnel Group.

China Railway Tunnel Group said it had bored the tunnel ahead of schedule. Once complete, the new highway is expected to cut travel time along the stretch from one hour to 20 minutes.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now