Responsive Image Banner

€3.5bn price hike for UK nuclear plant

Premium Content

Following a project review, energy firm EDF Energy has announced a delay to the delivery of Hinkley Point C nuclear plant on England’s Somerset coast, as well as a significant cost increase.

Construction work is ongoing at Hinkley Point C, Somerset, UK. Photo: Hinkley Point C

The French state-owned company – and majority owner of the plant – has set a new total cost for the project of between €29.5 billion and €30.7 billion, which is up to 44% more than its original cost estimate.

EDF further said it now has a target of June 2027, for the start of electricity generation from Unit 1 – a year later than had previously been estimated.

In a statement, EDF said, “During more than two years of the Covid-19 pandemic, the project continued without stopping. This protected the integrity of the supply chain and allowed the completion of major milestones.

“However, people, resources and supply chain have been severely constrained and their efficiency has been restricted.

“In addition, the quantities of materials and engineering as well as the cost of such activities, including, in particular marine works have risen.”

While the review took account of the main elements of the project, the schedule and cost of electromechanical works and of final testing were not included.

EDF is developing the Hinkley Point C plant as part of a joint venture with China General Nuclear Power Group (CGN).

The main contractor on the project is Bylor, which is a joint venture comprising Bouygues and Laing O’Rourke.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now