Disaster diverted: Florida causeway restoration reaches major completion

The Florida Department of Transportation (FDOT) announced substantial completion of the US$328 million Sanibel Causeway restoration project.

A repaired section of the Sanibel Causeway in Florida, US (Image courtesy Superior Construction) A May 2025 drone image of the repaired Sanibel Causeway in Florida, US. (Image courtesy Superior Construction)

The news comes nearly three years after Hurricane Ian (a Category 5 storm) caused catastrophic damage to the three-mi link (part of a larger 12-mi corridor) between Sanibel Island in San Carlos Bay and the Florida, US mainland.

Ian made landfall in September 2022 as a Category 4 storm, washing away large sections of the Sanibel Causeway and severing the only vehicular access to both the Sanibel and Captiva islands. The storm surge undermined roadbeds and collapsed multiple bridge approaches, making full reconstruction necessary to restore safe, permanent access.

US firm wins $404m worth of flood protection work on Port Arthur Project Kiewit has won a US$404 million contract to build additional portions of coastal storm risk management scheme

Construction focused on improving long-term storm resilience and included the installation of nearly 750,000 sq ft of steel sheet pile wall systems, more 19,000 linear ft of concrete caps, and nearly 128,000 tons of armour stone. Seawalls were elevated to heights between five and eight ft, and crews installed upgraded drainage infrastructure and a scour-prevention system using gabion marine mattresses and riprap.

Sanibel Causeway damage seen in 2022 after Hurricane Ian (Image courtesy Superior Construction) October 2022 image of the Sanibel Causeway damage caused by Hurricane Ian. (Image courtesy Superior Construction)

During peak construction, multiple specialised crews worked in parallel on pile-driving, earthworks, drainage, concrete, and asphalt, with traffic maintained on the causeway throughout.

The reconstruction was led by a joint venture of US-based firms Superior Construction and de Moya Group under a phased design-build contract (said to be the first of its kind for FDOT).

FDOT expects final paving and landscaping work, including restoration of recreational areas, to be completed by mid-2025.

Videos
Podcast: The EQ shift in construction leadership
Premium Content
Jevon Wooden on emotional intelligence’s role in boosting employee engagement and business performance 
Video: Perkins debuts a battery electric power unit at Bauma 2025
Perkins debuts its battery electric power unit technical demonstrator at Bauma in Munich, Germany
PODCAST: Kubota Execs Talk Autonomous Tech at CES 2025
Premium Content
Todd Stucke and Brett McMickell highlight the technology behind the company’s smart autonomous solutions
More Videos
Sponsored Content
STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: andy.brown@khl.com
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: neil.gerrard@khl.com
Catrin Jones Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: catrin.jones@khl.com
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: eleanor.shefford@khl.com
CONNECT WITH SOCIAL MEDIA