Equinor hit with nearly US$1bn impairment after offshore wind work halted by Trump

Norwegian energy company Equinor said it recorded a US$955 million impairment due to a forced temporary shutdown of its Empire Wind project off the coast of New York, according to its second-quarter earnings report.

Offshore wind turbines Offshore wind turbines. Image: Adobe Stock

The offshore wind project, one of the largest in the US, was halted in April by US Department of Interior Secretary Doug Burgum despite having previously received federal approvals. At the time, Equinor called the order “unprecedented and in our view unlawful.” Construction had already begun.

According to the company’s report, $763 million in losses were related to the Empire Wind 1/South Brooklyn Marine Terminal project and the remainder to the Empire Wind 2 lease.

While the work stoppage was later lifted in May, and construction has since resumed, the brief suspension coupled with rising material costs driven by new steel tariffs significantly impacted Equinor’s valuation of the project.

Equinor said cost pressures have mounted due to the high steel content of offshore turbines and support structures; under President Donald Trump’s tariff regime, offshore wind developers have faced increased prices for key imported components, particularly monopiles and transition pieces.

Despite the impairment, Equinor reported that higher US onshore gas production helped offset losses elsewhere. The company reported adjusted operating income for the quarter at $6.53 billion, down from $8.65 billion in Q1.

US halts construction of Equinor’s offshore wind project in New York The US Department of the Interior has ordered a halt to construction of Equinor’s Empire Wind offshore windfarm project off the coast of New York
STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Update: What do world’s biggest construction firms now spend on R&D?
The world’s largest construction companies continue to spend huge sums R&D. But how much exactly?
Project report: Robot used for power plant demolition
Sarens and Tadano carry out Dutch demolition project
Are humanoid robots really coming to a construction work site near you?
Robots have been threatening to take over work on construction sites for the past several years and haven’t. Will they eventually?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
World Construction Week newsletter

World Construction Week & Construction Briefing

Global project news, expert analysis and market trends, straight to your inbox.

Sign me up