Wyaralong Dam Project: Timeline
12 May 2009
The following timeline is indicative only and is dependent on relevant approvals and weather conditions during construction.
Late 2008
Temporary construction water pipeline activities commence
Access Road preconstruction activities commence
Early 2009
Access Road construction commences
May 2009
Successful dam alliance announced
Successful contractor announced for Beaudesert to Boonah Road Realignment
Late 2009
Access Road complete
Major works on dam construction commence
By Mid 2010
Beaudesert - Boonah Road realignment construction complete
By Mid 2011
Project complete in advance of required date
Courtesy: Queensland Water Infrastructure Pty Ltd