Wyaralong Dam Project: Timeline

12 May 2009

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralon

Queensland Dam Consortium has been appointed to build the AU$ 348 million (US$ 266 million) Wyaralong Dam by Queensland Water Infrastructure (QWI). Courtesy: Queensland Water Infrastructure Pty Ltd

The following timeline is indicative only and is dependent on relevant approvals and weather conditions during construction.

Late 2008

Temporary construction water pipeline activities commence

Access Road preconstruction activities commence

Early 2009

Access Road construction commences

May 2009

Successful dam alliance announced

Successful contractor announced for Beaudesert to Boonah Road Realignment

Late 2009

Access Road complete

Major works on dam construction commence

By Mid 2010

Beaudesert - Boonah Road realignment construction complete

By Mid 2011

Project complete in advance of required date

Courtesy: Queensland Water Infrastructure Pty Ltd

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA