Wind speed

Premium Content

25 November 2009

Meeting a tight deadline and coping with high winds were just two of the challenges faced by Bam in the construction of Europe's largest airport development in Berlin, Germany. The Berlin Brandenburg International airport (BBI) is one of the largest infrastructure projects currently under construction in Germany as well as being the largest airport development project in Europe.

Contractor Bam Deutschland was responsible for construction of the passenger terminal, which had a deadline of just 12 months.

Bam relied on Peri to supply the enormous quantities of slab, wall and column formwork for the placing of the 200000 m3 of reinforced concrete. A Peri spokesperson said, "The short construction period meant Peri engineers worked in close co-operation with Bam to create more than 400 formwork and assembly plans in just six months."

The slab tables and column formwork were pre-assembled by Peri as transportable units and delivered directly to the site. This saved on time, labor and storage space.

Due to the huge quantities of materials, slab tables and formwork elements were prefabricated in Berlin, Leipzig, Hamburg and at the co-ordinating centre for the project at Weissenhorn.

In order to meet the tight schedule, almost 2000 modular tables and 700 customized slab tables - designed together with Bam - were used for the project.

A Bam spokesperson said, "Site operations benefited from improved flexibility because even with high wind forces, work was able to continue without any interruptions. This was a very important factor at BBI which is regularly affected by such winds."

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Update: What do world’s biggest construction firms now spend on R&D?
The world’s largest construction companies continue to spend huge sums R&D. But how much exactly?
Project report: Robot used for power plant demolition
Sarens and Tadano carry out Dutch demolition project
Are humanoid robots really coming to a construction work site near you?
Robots have been threatening to take over work on construction sites for the past several years and haven’t. Will they eventually?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
Construction technology survey

Share your views and we’ll give to charity!

Take a quick survey on how you research equipment and we’ll donate £1 to Macmillan Cancer Support for every response.

Take the Survey