Transmission project to power 170,000 UK homes

Premium Content

13 September 2016

Artist's impression of E.ON’s 219MW offshore wind farm in the North Sea, 8km from the east Yorkshire

Artist's impression of E.ON’s 219MW offshore wind farm in the North Sea, 8km from the east Yorkshire coast, UK

A Balfour Beatty-led consortium has agreed a contract for the Humber Gateway offshore transmission project (OFTO) – a transmission link that will connect E.ON’s 219MW offshore wind farm in the North Sea, 8km from the east Yorkshire coast, to the onshore transmission grid.

The consortium sees Balfour Beatty link up with Equitix in the £162.9 million (€191.56 million) project, which will see the 73 turbines power around 170,000 UK homes per year.

The 20-year contract includes the operation and maintenance of the OFTO’s assets, including one offshore and one onshore substation, as well as two cable circuits consisting of 18km of subsea and 30km of land cable.

The European Investment Bank (EIB) is providing an £82 million (€96.42) 19-year loan for the Humber Gateway OFTO. Balfour Beatty, meanwhile, said it would invest £12.5 million (€14.70 million) of the total required equity of £21 million (€24.69 million).

Ian Rylatt, Balfour Beatty investments CEO, said, “This is our fourth OFTO contract to reach financial close and further establishes our position in the offshore transmission market.

“Our technical expertise ensures we can efficiently and effectively support the government’s targets to meet more of the UK’s energy needs through renewable sources.”

Meanwhile, Hugh Crossley, Equitix’s chief investment officer, said, “Equitix’s commitment to the offshore transmission market is testament to our investors’ appetite for long-term, availability-based, inflation-linked, UK infrastructure.

“We are pleased to be working in partnership with Balfour Beatty and Ofgem for the benefit of our investors and stakeholders”.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Liebherr LR 1300 comes of age and keeps on going
At 18 how does the 300 tonne capacity LR 1300 lattice boom crawler crane remain so popular?
Global construction equipment sales are still faltering. When will they recover?
Global construction equipment sales should start to come back from the bottom of the cycle next year, according to Off-Highway Research, but there is some uncertainty around the forecast 
Why construction needs to look forward if it wants to handle uncertainty
Dr Alan Manuel, group chief executive of Currie & Brown, on why the global consultant has launched a new Certainty Index
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
Construction technology survey

Share your views and we’ll give to charity!

Take a quick survey on construction technology and we’ll donate US$3 to Habitat for Humanity for every response.

Take the Survey