The tunnels

Premium Content

11 June 2008

Length: 9.7 km of twin track railway tunnel

Seven shafts for tunnel ventilation and emergency egress

Short mined adits to the bored tunnel

TBM: Mitsubishi Earth Pressure Balance

Diameter: 9.59 m

Length of first drive: Union Square Station to Burjuman Station, 1456 m, including passing under the Creek, with about 10 to 13 m cover to Creek bed and 22 m below Creek sea level

Lining: pre-cast bolted segmental lining, 400 mm thick, with ring taper

Geology: marine sand, overlying cemented sand and Sandstones

Water table: typically 3 to 4 m below ground level

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
D&RI100: The world’s largest demolition contractors
Was 2024 a year of transition for the industry?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now