New research examines why megaprojects fail

Premium Content

17 February 2020

Hinkley Point

A photo of the ongoing construction at mega project Hinkley Point C

Academics have studied the causes of mega projects that come in significantly over time and budget and have found that, while it is not possible to identify one factor leading to failure, there are six key factors.

The study, published in Project Management Journal, listed the six key factors as: decision-making behaviour; strategy, governance and procurement; risk and uncertainty; leadership and capable teams; stakeholder engagement and management; supply chain integration and coordination.

For the purpose of the study mega projects were defined as those at a cost of over US$1 billion.

Lead researcher Dr Juliano Denicol, UCL School of Construction & Project Management, said, “Considering the importance of megaprojects to the global economy, we aimed to deepen and extend our understanding of the causes and cures of poor megaproject performance.

“We have emphasised the solutions rather than problems, in an attempt to shape the academic conversation to a more positive discourse and connect with the needs of senior managers delivering megaprojects.”

Academics analysed over 6,000 academic summaries and filtered these down to 86 papers which were fully analysed.

The findings were presented, assessed and verified in two workshops involving academics and senior practitioners from UK megaprojects including Crossrail, Thames Tideway Tunnel, High Speed Two and Hinkley Point C.

The team has set a research agenda and proposed five future avenues to advance the successful delivery of megaprojects. These are: Designing the system architecture; bridging the gap with manufacturing; building and leading collaborations; engaging institutions and communities; decomposing and integrating the supply chain.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Building at the bottom of the world: Final season constructing an Antarctic research facility
British Antarctic Survey’s project manager David Brand on the challenges of building in Antarctica as handover of Discovery Building draws closer
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now