Bauer Engineering India Pvt. Ltd., a subsidiary of Bauer, has been helping the construction of a new hydroelectric power plant on the Arun River in Nepal, which flows from Tibet through the Himalayas into China.

The company was tasked by Indian company Jaiprakash Associates with the construction of a cut-off wall as part of the project Arun III HEP. The goal is to achieve a seal and reduce seepage water below the upstream cofferdam and in the left and right abutments.

The scope of service provided by Bauer includes the execution of 3,500 running meters of drilling and injection work on the cofferdam. In the granular construction soil, composed of sand, gravel, rubble and boulders, the pore injections are executed by means of tube-à-manchette and annular grouting

“Using the pore injections, we are able to fill the pores in the very loose soil with cement slurry and thereby reduce its permeability,” said Satish Kumar, project manager.“Injections require a high degree of quality assurance and quality control. We are able to meet the strict demands thanks to our many years of experience.”

In addition to the pore injections, Bauer will also carry out rock grouting in order to fill gaps, fractures and cavities in the rock.

Due to the remote location in the Himalayas, both construction soil and logistics pose challenges. The schedule is very tight: this is because snow starts to melt in March, causing the water level in the river to rise and making work more difficult.

The work executed by Bauer started in December 2021 and is expected to be completed by May 2022. The new hydroelectric power plant is expected to produce up to 900MW of electricity.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
What is the Genie business worth and what type of buyer could it attract?
What could happen following Terex’s announcement that it will sell or spin off its Genie aerials business?
EU Pay Transparency Directive: what will it mean for international construction businesses?
With less than a year to go until the European Union’s (EU) Pay Transparency Directive takes effect, what does it mean for international construction businesses?
5 ways formwork and falsework are evolving
At first glance, formwork and falsework is a simple-enough concept, vital though it is for temporary works.
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Inside The Minds of Leaders:
Using Tech To Unearth Greater Profit

FREE WEBINAR ON-DEMAND

This session was hosted by KHL's Mitch Keller, with speakers from AEM, Landmark Construction and Trimble.

Download and watch in your own time