Responsive Image Banner

LNG infrastructure

Premium Content

11 June 2008

When the Shanghai Liquified Natural Gas (LNG) project is completed, it will comprise a storage capacity of 6 million tonnes, a high-capacity distribution grid and a berthing terminal for superheavy tanker vessels.

The three large storage tanks will be 52 m high, with an inside diameter of 40 m. They feature a double-skin design to prevent leaks, with the steel inner tank housed inside an 800 mm cast in-situ concrete shell. The contracting consortium, comprising Shanghai Electric Power Construction Company and China Nuclear Industry Huaxing Construction Company, is building these using Doka's 150F climbing formwork.

The formwork system for each tank comprises 192 150 F units along with 1020 m2 of Top 50 large-area formwork. Thanks to the fact atht the forms are self climbing, saving on crane time, it has been possible to work on a weekly cycle. The formwork is joined to the climbing scaffolding to make a unit which can be lifted in one piece from one casting section up to the next, in a single crane cycle. No crane assistance is needed for setting up and striking the formwork. This greatly reduces the craneage needed for the forming operations, hugely simplifying the site logistics.

The site engineers were particularly impressed by the user safety and ease of handling offered by this climbing formwork system. "The scissor-action spindles enabled us to manoeuvre the timber-beam formwork into the pouring position quickly and accurately. Also, the broad-sized working platforms, with a 700 mm retracting distance for the formwork, leave plenty of space for cleaning the form-ply", said project manager Chenwu Li.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Project report: Robot used for power plant demolition
Sarens and Tadano carry out Dutch demolition project
Are humanoid robots really coming to a construction work site near you?
Robots have been threatening to take over work on construction sites for the past several years and haven’t. Will they eventually?
Bentley Systems’ Nathan Marsh: why being first with AI isn’t always best
At Bentley’s Year in Infrastructure event, Nathan Marsh outlined why trust, authenticity and human oversight still matter in the AI age
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
World Construction Week newsletter

World Construction Week & Construction Briefing

Global project news, expert analysis and market trends, straight to your inbox.

Sign me up