Hydrodemolition challenge

Premium Content

15 April 2008

The 1 Km long multi span steel box girder Moerdijk Bridge, over Holland's Diep river near Dordrecht in the southern Netherlands, is a major structure on the vital E19/A16 European highway through Holland and Belgium. The current 45m wide, dual three lane bridge, opened in the late 1970s and built on the original concrete piers of the previous structure, is believed to be one of the most heavily trafficked bridges in Europe, carrying around 120000 vehicles a day.

After a routine inspection revealed fatigue cracking of the deck plate, the Dutch Ministry of Transport designed a € 10,5 million restoration plan. This involves repairing the cracks followed by what is believed to be one of the first major applications of a thin – 50 to 70 mm – 105 MPa high strength concrete wearing course overlay.

Prior to replacement, sections of the existing high strength concrete had to be removed without damaging the steel deck. Contractor Haverkort Voormolen chose hydrodemolition using a Conjet 432 Robot – the largest in the range – for this task.

“We have to remove about 130 m3of this heavily reinforced, extremely high strength concrete, which, due to the uneven deck plate, varies in thickness from 50 to 70 mm. This is the toughest hydrodemolition job I have been involved with,” said project engineer Elwin Roelfsema.

He continued, “Hydrodemolition with the Conjet 432 Robot has proved to be a very safe and effective way of removing the damaged sections of high strength concrete overlay. There is no other method we could have used without damaging the deck plate.”

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Project report: Robot used for power plant demolition
Sarens and Tadano carry out Dutch demolition project
Are humanoid robots really coming to a construction work site near you?
Robots have been threatening to take over work on construction sites for the past several years and haven’t. Will they eventually?
Bentley Systems’ Nathan Marsh: why being first with AI isn’t always best
At Bentley’s Year in Infrastructure event, Nathan Marsh outlined why trust, authenticity and human oversight still matter in the AI age
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
World Construction Week newsletter

World Construction Week & Construction Briefing

Global project news, expert analysis and market trends, straight to your inbox.

Sign me up