Gateway Bridge update

14 May 2009

Duplication of the second Gateway Bridge, part of the AU$ 1.88 billion Gateway Upgrade Project, Bris

Duplication of the second Gateway Bridge, part of the AU$ 1.88 billion Gateway Upgrade Project, Brisbane, Australia is now just over two years into construction.

The 750 m northern approach (pictured) has been constructed using a segmental match-casting method, which is also being used to construct the 350 m-long southern approach.

The 260 m-long main span and 130 m-long side spans are being constructed using a cast insitu method, casting segments at height from the two main piers.

The project is being delivered by Queensland Motorways with design and construction by the Leighton Abigroup Joint Venture.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]