French nuclear project hit by more delays

Premium Content

10 October 2019

flamanville nuke

The Flamanville nuclear reactor

Electricite de France (EDF) says repair work on faulty welding at the Flamanville nuclear plant in northwest France will cost €1.5 billion.

The additional work will push the total cost of the project up by some 4%, to approximately €12.4 billion.

The repair work was demanded by the French nuclear watchdog ASN, following inspections; now EDF says its preferred approach to the repairs is to use robot welding.

The new welding, however, is unlikely to be ready for inspection by ASN before the end of 2020.

In a statement, EDF said, “The provisional schedule…results in the date of fuel loading at the end of 2022.” This would mean the reactor coming online some time in 2023 – four years later than initially anticipated.

EDF shares fell 1% following the news and are down more than 36% this year, adding to the company’s woes, which include delays and cost hikes on two similar reactors in the UK.

Longer reads
How is Terex’s sale of Genie progressing?
Simon Meester, CEO of Terex, provides updates on the work to seperate Genie and its search for a buyer during Q3 earnings call 
Kobelco’s three objectives after buying 70% of CNH’s construction machinery arm
Japanese construction equipment manufacturer Kobelco has set out three objectives at the heart of its move to buy 70% of CNH Industrial’s construction machinery business
Different approaches to cranes and lifting for data centre construction
Prolific data centre construction is seeing different approaches to lifting
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson VP Sales – Construction Division Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA