FCC raises the roof

Premium Content

25 January 2017

FCC elevating the roof of the Wanda Metropolitano in Madrid

FCC elevating the roof of the Wanda Metropolitano in Madrid

Spanish-based contractor FCC has started elevating the roof of the Wanda Metropolitano, the new stadium of Atlético Madrid football club in the Spanish capital.

FCC said that it differed from other recent European sports facilities, as the modern roof design is formed of a steel structure weighing more than 5,700 tonnes.

It is tensioned with radial cables bound by a membrane that occupies a surface area of 83,053m2.

The roof is an open tensile structure comprising an exterior steel and double height compression ring, an interior traction ring and two sets of radial cables. The roof will shelter the stands, protecting 96% of seats from the rain.

The new stadium is being built by FCC and was designed by architects Antonio Cruz and Antonio Ortiz. It will take up a total surface area of 145,721m2 and will have a 67,000 seating capacity, distributed into stands, boxes and a VIP area. It will also offer more than 4,000 parking spaces.

The distribution of the new seating blocks will bring fans closer to the football pitch, with three new T-shape blocks. They are formed of a lower block made up of 28 floor stands and priority zones, a mid-level block of 13 stands for VIPs with direct outdoor access, and a high-level block supported on a wrap-around building comprising 32 stands. This is where the public enter, and VIP boxes and complementary services are located there as well. An area with 79 boxes has also been built at the lower part of the high-level block.

Longer reads
How is Terex’s sale of Genie progressing?
Simon Meester, CEO of Terex, provides updates on the work to seperate Genie and its search for a buyer during Q3 earnings call 
Kobelco’s three objectives after buying 70% of CNH’s construction machinery arm
Japanese construction equipment manufacturer Kobelco has set out three objectives at the heart of its move to buy 70% of CNH Industrial’s construction machinery business
Different approaches to cranes and lifting for data centre construction
Prolific data centre construction is seeing different approaches to lifting
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson VP Sales – Construction Division Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA