Lengths of pipe wait to be laid in the ground along the under-construction Mountain Valley Pipeline near Elliston, Virginia, U.S. September 29, 2019. Picture taken September 29, 2019. REUTERS/Charles Mostoller

The cost of the Mountain Valley Pipeline (MVP) project, a natural gas pipeline system that spans approximately 303 miles from northwestern West Virginia to southern Virginia in the US, has risen from US$6.6 billion to US$7.2 billion. Its completion date has also been pushed back.

The MVP project has faced numerous regulatory hurdles and lawsuits since it was first announced in 2014. Construction on the project began in 2018.

It is being built by a joint venture composed of Equitrans Midstream, NextEra Energy, Consolidated Edison, AltaGas and RGC Resources. Its opening has been delayed from this year to the first quarter of 2024.

Part of the reason for the delay and cost increase is said to be difficulties finding workers with the required experience willing to work on a project that has been halted previously due to legal challenges.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
5 ways formwork and falsework are evolving
At first glance, formwork and falsework is a simple-enough concept, vital though it is for temporary works.
Global construction equipment sales are still faltering. When will they recover?
Global construction equipment sales should start to come back from the bottom of the cycle next year, according to Off-Highway Research, but there is some uncertainty around the forecast 
Why construction needs to look forward if it wants to handle uncertainty
Dr Alan Manuel, group chief executive of Currie & Brown, on why the global consultant has launched a new Certainty Index
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Inside The Minds of Leaders:
Using Tech To Unearth Greater Profit

FREE WEBINAR ON-DEMAND

This session was hosted by KHL's Mitch Keller, with speakers from AEM, Landmark Construction and Trimble.

Download and watch in your own time