Bidding on Belo Monte Dam suspended

Premium Content

16 April 2010

A Brazilian federal court judge has suspended bidding for the construction and operation of the Belo Monte Dam on the Xingu River in the Amazon.

The ruling has resulted in the suspension of the hydroelectric project's environmental licence that was granted by the Brazilian Institute of Environment and Renewable Natural Resources (IBAMA) in February this year.

Brazilian president Luiz Inacio Lula da Silva has vowed to appeal the ruling. Executive director of pressure group Amazon Watch, Atossa Soltani said, "Everyone recognises that in Brazil a decision like this could be overturned quickly, so we clearly haven't won the battle yet."

Bidding by a single consortium for the construction and operation contract was scheduled to take place on 20 April, but the judge said that more time was needed to examine claims that indigenous people were not consulted about the project and that insufficient clauses regarding environmental protection were in place.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now