Work on major pipeline halts

05 January 2018

Pa pipeline land flickr.5978a6799fb3d

Work on the pipeline has been halted

Pennsylvania regulators have ordered construction crews to stop work on a major pipeline after recording numerous environmental violations in the building process, including spills and well contamination.

The Pennsylvania Department of Environmental Protection (DEP) accused Sunoco Pipeline of, “egregious and willful violations” of environmental rules in building the Mariner East 2 pipeline.

The agency ordered the company to halt all work except some maintenance activities on the pipeline until it can demonstrate that it is abiding by all requirements from the permits the state granted.

“Until Sunoco can demonstrate that the permit conditions can and will be followed, DEP has no alternative but to suspend the permits,” DEP Secretary Patrick McDonnell said in a statement. “We are living up to our promise to hold this project accountable to the strong protections in the permits.”

Sunoco is a subsidiary of Energy Transfer Partners, the Dallas-based company that developed and operates the contentious Dakota Access pipeline in the Great Plains.

The pipeline, costing more than $2.5 billion, is designed to carry propane, ethane, and butane approximately 350 miles from southwest Pennsylvania to an export terminal at Marcus Hook near Philadelphia. 

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA