Robbins Crossover XRE breaks record as World’s fastest TBM

Premium Content

16 November 2021

Turkish TBM breaks through completing Esme-Salihli Railway Tunnel

Personnel from contractor Kolin Construction and Robbins celebrate the breakthrough of a Crossover (XRE) TBM

Records were broken when the 3.05km long Esme-Salihli Railway Tunnel in Turkey was completed last month. A team made up of employees from Kolin Construction, Turkish State Railways (TCDD), and Robbins witnessed the breakthrough of the world’s fastest TBM over 13m in diameter.

The 13.77m XRE TBM set world records three times over, beating its own records in May and June with a set of records over the summer, including a best day of 32.4m, a best week of 178.2m, and a best month of 721.8m.

Launched in March 2021, the machine bored 3.05km on the Esme-Salihli Railway Tunnel as part of the Ankara-İzmir High Speed Railway Project for the TCDD.

“When the strength, force and torque generated by our Crossover TBM are taken into account, we consider it to be a beast. It has performed extremely well in this tunnel,” said Onur Kansu, TBM Manager for project contractor Kolin Construction. He added, “We are proud we have accomplished such high performance.”

The machine began its bore in altered gneiss, then passed through mélange consisting of gneiss, sandstone, claystone, mudstone, quartz, and silt, as well as a section of mudstone.

The Robbins Crossover TBM set multiple records, including a best day of 32.4 m (106 ft)

The project is said  to be particularly important for the Turkish tunnelling industry. “We have disproved the idea that it is difficult to reach high advance rates while boring in EPB mode with large diameter TBMs. Crossover TBMs enable us to find quick solutions in changing ground, so we believe they will be the preference for future projects,” said Kansu.

With tunnel excavation finished, work will continue on the 508km line that will connect Polatlı in Ankara Province to Izmir, the third most populous city in Turkey. Once complete, the Ankara-İzmir High Speed Railway will be the longest rail line in the country, conveying passengers at top speeds of 250km/h in a railway journey of about 3.5 hours.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now