McCarran's T3 reaches halfway

Premium Content

15 January 2010

McCarran International Airport's new Terminal 3 is part of a US$ 4 billion expansion.

McCarran International Airport's new Terminal 3 is part of a US$ 4 billion expansion.

A tour of Las Vegas' McCarran International Airport's under-construction Terminal 3 (T3) this week by Nevada's Democratic senator Harry Reid marked the halfway point of the US$ 2.4 billion project.

Construction of the 14-gate T3 has been divided into six "major elements." At present its foundations and utility corridors are finished, the central utility plant is nearly complete, the interior fit out of the main terminal building is underway and a series of new roads giving access to the terminal is more than 60% complete.

An eight-level parking garage is also nearing its halfway point, and construction of the aircraft apron is in its early phases. A solar power array will eventually be installed on top of the parking garage roof.

Perini Corporation subsidiary Perini Building Company won the US$ 1.2 billion contract to construct T3's main building in July 2008 with construction starting in August.

Started in 2008 and due for completion in 2012 the new 174000 m² terminal is part of a US$ 4 billion expansion plan that started with the adoption of a master plan in 2008.

About 1800 workers were on site when construction reached its peak in December 2009.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Why construction needs to look forward if it wants to handle uncertainty
Dr Alan Manuel, group chief executive of Currie & Brown, on why the global consultant has launched a new Certainty Index
‘European Rental Week’ puts cost control and sustainability in spotlight
As the third European Rental Week gets underway, Construction Briefing talks to leaders in Europe’s equipment rental industry about the relevance of rental in today’s construction sector.
Inside Saudi Arabia’s construction surge: three key takeaways
From Diriyah to Qiddiya, Saudi Arabia is building on an unmatched scale as Vision 2030 reshapes the kingdom’s skyline
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
Construction technology survey

Share your views and we’ll give to charity!

Take a quick survey on construction technology and we’ll donate US$3 to Habitat for Humanity for every response.

Take the Survey