How a $3.7bn construction project aims to protect communities near New Orleans from hurricanes

Work underway on the West Shore Lake West Pontchartrain project Image supplied by USACE

The devastation wrought by Hurricane Katrina on New Orleans and the wider Gulf Coast in 2005 lives long in the memory.

The deadly hurricane caused 1,836 deaths and damage estimated between US$97.4 billion to $145.5 billion.

While that was the worst hurricane to hit the region in living memory and the costliest ever to hit the United States, the area was also battered by Hurricane Isaac in 2012 and Hurricane Ida in 2021. Isaac in particular caused tens of billions of dollars’ worth of damage in Louisiana.

Against that backdrop, the $3.7 billion West Shore Lake Pontchartrain (WSLP) Hurricane and Storm Damage Risk Reduction project could pay for itself in relatively short order, although costs on the project have risen significantly (see below).

Map of the West Shore Lake Pontchartrain scheme Image: USACE

Overseen by the US Army Corps of Engineers (USACE), it aims to provide over 60,000 residents across three parishes – St. John the Baptist, St. James and St. Charles Parish – with a 100-year level risk reduction.

The work involves building a massive, 18-mile-long levee system in remote locations and often on challenging terrain. The first contracts were awarded late last year and work is expected to carry on through to late 2027.

To provide that 100-year level risk reduction, US Army Corps of Engineers (USACE) and its team has made calculations using specialist computer software called ADCIRC to run a suite of 37 different storm types through the project area.

The calculations give surge and wave statistics to help predict how the levees will perform, says Bradley Drouant, USACE senior project manager, New Orleans District.

As things stand, USACE has already awarded or is close to awarding eight contracts that account for 13.8 miles of the 18-mile levee system.

Drouant says, “The first levee construction contract, WSLP-110 near Garyville, was awarded December 2022. WSLP-107 was awarded in March 2023. Construction on the third and most eastern levee reach, WSLP-101a, was awarded in April 2023. The fourth and fifth levee reach construction contracts, WSLP 108 and 104 respectively, were awarded in August 2023. WSLP-102 and WSLP-106 were awarded in September 2023.”

Another contract, WSLP-105 was awarded the end of September (see box below).

Work underway on the West Shore Lake West Pontchartrain project Image supplied by USACE

Those awards follow the construction of nine “land bridge” access roads from existing state highways and the Interstate Highway 10 (I-10) to the future levee alignment.

Those access roads are essential because the marshy, sparsely populated areas where construction is underway makes for difficult working conditions.

“A primary difficulty of the WSLP project is the location,” says Drouant.

“The conditions of the marsh make it especially difficult to mobilize equipment and to complete construction.

“The accessibility of sites for workers, materials, and equipment is also a challenge.

Want to see more construction insights?
Sign up to the
Construction Briefing

“However, it is one we are prepared for by awarding a $16m contract to provide ‘land bridge’ access roads through the marsh. We overcome the challenges of this project through preparation and planning.”

Other works in advance of the levee construction included two sand placement contracts in the WSLP-101/102/103 reaches, pile load test contracts, three stockpile contracts for sand and clay, and multiple mitigation bank awards.

Portrait image of Bradley Drouant Bradley Drouant

USACE expects to continue awarding levee construction contracts through autumn 2024.

Meanwhile, efforts are underway to design the project’s western tie-in levee, which will link with Louisiana’s Maurepas Diversion project.

The Maurepas Diversion is a swamp mitigation feature of the WSLP project to compensate for What USACE calls “unavoidable impacts” to swamp habitat.

Future work by USACE includes two additional levee contracts, two floodgate contracts, and a contract for two major 2,000 cubic feet per second (CFS) pump stations in St. John the Baptist and St. Charles Parishes.

The Coastal Protection and Restoration Authority and the State of Louisiana are expected to award three levee reaches and the Maurepas Diversion as a single contract. There is a separate Corps contract planned to provide risk reduction in St. James Parish.

Rising costs

While the entire project originally had a budget of $760 million allocated to it (based on 2014 economic conditions), USACE announced earlier this year that costs have risen considerably.

In July this year, it set out reassessed project costs including the requirement for an additional $1.27 billion to deliver WSLP to its authorized levee elevations and to complete the system’s pump stations and drainage structures.

On top of that, the USACE said it would need another $1.7 billion for environmental impact mitigation efforts and future levee lifts to ensure that the authorized level of risk reduction is maintained throughout the project’s 50-year design life.

Col. Cullen Jones, New Orleans District Commander, said, ““An increase in project cost has become common throughout the nation, for not only Corps of Engineers constructed projects, but also for goods and services due to ongoing supply chain issues.

“We will continue to press forward in completing the ongoing work as well as awarding new construction contracts while simultaneously pursuing every option for securing additional funds required to deliver this system.”

Lasting legacy

Despite those inflating costs, the project team involve are hopeful that their work will leave a lasting legacy in the area.

Drouant says: “Personally, I am ecstatic to have the opportunity to contribute to this project.

“I am very pleased with the entire team of our non-federal sponsors (Coastal Protection and Restoration Authority and Pontchartrain Levee District) and the personnel here at the New Orleans District. The significant effort and coordination the team has contributed over the years has made the award of these contracts possible.

“The project delivery team is composed of highly motivated individuals eager to provide a finished project to the citizens of St. John the Baptist, St. James, and St. Charles Parishes to help reduce the risk to their lives, property, and prosperity.”

Recent levee construction contract awards

22 December 2022: Lemoine-Frazier of Lafayette, Louisiana won a $9.4 million contract for the construction of a one-mile-long stretch of levee in St. John the Baptist Parish under contract 110. Work is due for completion in 2024.

16 March 2023: B&K Construction of Mandeville, Louisiana won contract 107, worth $25.5 million, to build 1.7-mile-long stretch of levee at an elevation of 9.6 feet in St John the Baptist Parish.

28 April 2023: Onshore Materials of Thibodaux, Louisiana won a $22.6 million contract for the construction of levee reach 101a, which is 1.8 miles long and an elevation of 12.5 feet.

23 August 2023: Dynamic Group of Baton Rouge, Louisiana won contract 104, for the construction of a 2.5-miles-long stretch of levee at a height of 11.5 feet (3.5m) and a pipeline crossing floodwall in St. John the Baptist Parish. The contract is worth $38.9 million.

25 August 2023: EvCo Development of Lafayette, Louisiana won contract 108 to build a 1.5-mile section on the fourth levee reach at an elevation of 8.6 feet in St. John the Baptist Parish. The contract value is $22.4 million.

12 September 2023: $49.8 million contract awarded to Dynamic Group for the one-mile-long, 11-foot high fifth levee reach (contract WSLP-106) in St. John the Baptist Parish. Completion due in summer 2027.

14 September 2023: $84.4 million contract award to B & K Construction for the sixth levee reach in St. John the Baptist Parish. The 1.3-mile section will be at an elevation of 13.9 feet and comes under the WSLP-102 package of works. Completion due in summer 2027.

22 September 2023: $59.2 million contract award to Onshore Materials to build the eighth levee reach on the WSLP project in St. John the Baptist Parish. The three-mile stretch at 11 feet elevation falls under the WSLP-105 package of work. Completion due in late 2027.

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA