Big Carl’s first major lift at HPC

12 February 2020

The 5,000 tonne capacity Sarens SGC-250, aka Big Carl, has completed its first major lift at Hinkley Point C nuclear power station in the UK. It was the first of more than 700 lifts that the SGC-250 will perform here over the next four years, on behalf of client Bylor and project owner EDF/ NNB. The loads will range from precast concrete elements to pipe sections, steel rings, and machinery equipment weighing from 10 to 1,600 tonnes. The SGC-250 will also lift five major parts of each unit’s steel containment liner and dome.

92536_Liner Cup Lift - 18th Dec 2019 - 005

Saren’s SGC-250 has completed its first major lift at HPC
STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA