Video: ‘Big Carl’ crane lifts dome for Hinkley Point C’s first reactor building into place

Premium Content

The world’s biggest crane, known as ‘Big Carl’, has lifted the dome for the first reactor building at UK nuclear power plant Hinkley Point C in Somerset into place.

The work paves the way for the first nuclear reactor to be installed next year.

Engineering teams lifted the 245-tonne, 14m-high steel dome onto the 44m-high reactor building on 15 December.

The 47m-diameter dome is the top part of the reactor building’s inner containment – a steel cylinder encased in concrete. It is made up of 38 prefabricated panels which were shipped to Hinkley Point C and welded together in an onsite factory.

Earlier this month, the 750 tonne “Polar Crane” was lifted into place in a single piece above the reactor building’s third – and final – steel liner ring. This internal crane will rotate 360° above the reactor and be used for refuelling and installing equipment.

At 47 metres in diameter the dome is wider than the dome of St. Paul’s Cathedral’s in London. At 47 metres in diameter the dome is wider than the dome of St. Paul’s Cathedral’s in London. (Image courtesy of EDF)

Bylor, a joint venture between contractors Bouygues and Laing O’Rourke, is building the nuclear power plant for client EDF Energy.

Simon Parsons, nuclear island area director, said: “Building the first nuclear power station in a generation is a challenging job and the success of this complex operation is due to the determination and commitment of our fantastic teams.

“Lifting the dome allows us to get on with the fitting of equipment, pipes and cables, including the first reactor which is on site and ready to be installed next year.”

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
What is the Genie business worth and what type of buyer could it attract?
What could happen following Terex’s announcement that it will sell or spin off its Genie aerials business?
EU Pay Transparency Directive: what will it mean for international construction businesses?
With less than a year to go until the European Union’s (EU) Pay Transparency Directive takes effect, what does it mean for international construction businesses?
5 ways formwork and falsework are evolving
At first glance, formwork and falsework is a simple-enough concept, vital though it is for temporary works.
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Inside The Minds of Leaders:
Using Tech To Unearth Greater Profit

FREE WEBINAR ON-DEMAND

This session was hosted by KHL's Mitch Keller, with speakers from AEM, Landmark Construction and Trimble.

Download and watch in your own time