Two firms to build new tunnel to prevent Hong Kong flooding
13 October 2026
The Hong Kong skyline at night (Image: Funny Studio via AdobeStock - stock.adobe.com)
Bouygues Construction and China Road and Bridge Corporation (CRBC) have won a contract to build a new drainage tunnel to prevent flooding in Hong Kong.
The two firms will share a €173 million contract awarded by the Drainage Services Department of the Hong Kong Special Administrative Region to build the Hong Kong East Drainage Tunnel (HKEDT).
Once completed, the tunnel will collect rainwater from upstream catchment areas and channel it to Pak Sha Wan, a nearby discharge point into the sea.
Bouygues said the tunnel would relieve pressure on the existing downstream drainage network and reduce the risk of flooding in the Eastern District of the island, “where impermeable surfaces and high urban density are significantly worsening the risk of flooding”.
The project includes the construction of a 3.6-kilometre drainage tunnel, approximately five metres in diameter, which will link the districts of Shau Kei Wan and Chai Wan, on the east coast of Hong Kong Island, to Pak Sha Wan.
The consortium will also build seven intake structures to collect and capture surface runoff before it reaches built-up areas, six connection tunnels (adits), and an outfall structure which discharges water from the tunnel into the sea.
Bouygues said excavation would involve a tunnel boring machine (TBM), drill-and-blast excavation, the drill-and-break method for excavating rock and large concrete structures, and pipe jacking.
The complex project is scheduled for completion in 2030.
Bertrand Burtschell, deputy CEO of Bouygues Construction with responsibility for civil works, said, “Some twenty years after we handed over the Hong Kong West Drainage Tunnel, this project is testament to our continued presence in this region and the trust that has been placed in our expertise to construct complex and essential infrastructure. Alongside our partners, we are continuing our commitment to strengthening the resilience of this region and providing its residents with better protection against extreme weather events.”
CONNECT WITH THE TEAM