Jacobs extends role on troubled €3bn green steel plant in Germany
24 September 2026
US-based project management and consulting firm Jacobs has extended its role on a €3 billion ‘green’ steel plant in Germany.
Thyssenkrupp Steel’s plant a Duisburg (Image: Thyssenkrupp)
Thyssenkrupp Steel’s direct reduction plant in Duisburg, Germany, was originally awarded a programme and construction management contract for the plant in August 2023.
In August this year, Thyssenkrupp negotiated a deal with the European Commission to ensure the plant could go ahead despite changed conditions.
The company secured €2 billion in public funds for the plant in 2023, with the condition that it would hydrogen produced using renewable energy.
However, hydrogen is unlikely to be available in Europe at affordable prices in the near future. Thyssenkrupp has said the plant could also run on natural gas.
Jacobs said it would continue to coordinate design, logistics and construction.
Once complete, the “hydrogen-capable” plant is expected to produce approximately 2.5 million metric tons of direct reduced iron (DRI) a year, replacing coal-powered blast furnaces.
On site, Jacobs supervises civil works, logistics, quality assurance and works closely with Thyssenkrupp to support health, safety and environmental performance, and manages assembly logistics and onsite material flow between the contractors.
SMS group, based in Düsseldorf, holds a contract for the engineering, delivery and construction of the plant.
Jacobs executive vice president Fiachra Ó Cléirigh said, “This contract amendment and extension reflects the trust Thyssenkrupp has in our team to bring this complex, first-of-its-kind hydrogen-based iron making facility online. We’re focused on delivering this project to support the shift toward climate-neutral steelmaking and deliver on our promise of a more connected, sustainable world.”
Thyssenkrupp Steel executive director Construction DR Plant Ulrich Greiner Pachter added, “The contract extension is the result of the constructive and reliable collaboration we have established with Jacobs since the start of the project. Jacobs has been a valuable partner in coordinating the many interfaces of this complex transformation project.”