Hoover bypass opening delayed

Premium Content

29 April 2008

Construction of the US$ 234 million Hoover Dam bypass (see iC March 2005) has been delayed following the collapse of a giant cableway system in 63 mph (100 km/h) winds. No one was hurt in the collapse, which happened on 15 September.

Although the collapse occurred during particularly high winds, investigators are yet to determine the exact cause, although metal fatigue has not been ruled out. As a result of the collapse, traffic along US Highway 93, which crosses the dam, has bee rerouted.

The 762 m cable, which was supported by two 100 m high towers, was used to deliver steel girders and pre-cast concrete sections during construction of the 597 m long, 26.8 m wide, US$ 114 million concrete deck arch bridge contract.

Designed to carry a maximum load of 50 tons (45.4 tonnes) of material over the Colorado River, the joint- venture of Obayashi Corporation and PSM Construction purchased the 42-year-old refurbished system from the American Bridge Company, and was key to the joint venture winning the project.

According to the Federal Highway Administration, work is likely to be delayed for “a couple of months”. The project is scheduled to finish in 2008 but is approximately four months behind schedule following a dispute over concrete suppliers.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
D&RI100: The world’s largest demolition contractors
Was 2024 a year of transition for the industry?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now