Design failures behind 40% of construction disputes
02 November 2026
Design-related failures contributed to claims and disputes on more than 40% of construction and engineering projects examined in a global study, with nuclear and data centre developments facing particularly high levels of financial risk.
Global study of projects worth US$2.56 trillion reveals major risks facing nuclear, data centre and renewable energy construction. Image: Adobe Stock
The ninth annual CRUX Insight report, published by consultancy HKA, analysed 2,410 projects across 122 countries, representing a combined investment of US$2.56 trillion.
The research found that design-related problems contributed to disputes on 40.5% of projects, including design errors (20.8%), late design information (19.7%) and incomplete designs (17.2%). Changes in project scope were another major cause, affecting 33.4% of projects.
Across the dataset, claims for additional costs averaged 33% of contract budgets, while claims for extensions of time amounted to 65.8% of planned project schedules.
HKA said the cumulative value of sums in dispute across the projects had reached US$100 billion.
Nuclear and data centre risks
Nuclear construction emerged as a particular area of concern, with sums in dispute on more recent projects averaging 122% of contracted budgets.
Late design information was identified as a cause of disputes on 41.7% of nuclear projects, with HKA pointing to political pressure to begin construction before planning and design work had been completed.
Data centre construction also showed significant financial pressures. Although claimed extensions of time fell from an average of 112% of planned schedules across the wider dataset to 67% on projects scheduled to complete from 2020 onwards, disputed costs increased from 20.6% to 30.2% of budgets.
The report identified incomplete and inaccurate designs, as well as difficulties installing complex building services and integrating critical systems, as major contributors to data centre project disputes.
Renewable energy projects faced different challenges, with unforeseen physical conditions affecting 23.7% of projects and restricted or delayed site access contributing to disputes on 18.7%.
HKA also highlighted problems involving inexperienced contractors, particularly in offshore wind cable installation, alongside supply chain constraints.
Despite these pressures, the research found evidence that project outcomes are improving. Across projects scheduled to complete from 2020 onwards, average claimed extensions of time fell to 48.8% of planned schedules, while contested costs declined to 28.4% of contract budgets.
HKA’s findings are based on projects involving claims or disputes investigated by its consultants, rather than a representative sample of all construction projects. The reported figures reflect amounts claimed or disputed, not necessarily final cost overruns or sums awarded.