Construction project delays up 100% due to Covid

Premium Content

Delays to large-scale construction projects have more than doubled during the Covid-19 pandemic, according to new data released by machine learning company nPlan.

Researchers at tech firm nPlan found that the median delay for projects completed before the pandemic was approximately 100 days, while pandemic-era projects have a median delay of more than 200 days.

Analysis of pre- and mid-pandemic projects in the nPlan schedule dataset suggests that nearly nine in ten large-scale construction projects (85.5%) are delivered late – nearly two-thirds of them (59.4%) by at least two months.

Nearly one in four projects (22.7%) are delivered more than 250 days late, while more than one in ten (13.4%) are delayed by at least a year.

The machine learning startup has amassed a dataset of more than half a million construction schedules through its work with companies including Network Rail, Shell, Kier and Google. The data includes schedules from UK, Europe, Australia and America.

Dev Amratia, CEO of nPlan, said, “In construction, as in so many other sectors and areas of public life, the pandemic hasn’t just created new problems, it has highlighted and exacerbated existing problems – in this case the costly project overruns which are endemic to the industry. Because this issue was not dealt with before the pandemic, we are now in a situation where projects have suddenly become much riskier.

“This will pile pressure on contractors and may mean clients bring forward fewer projects. On the other hand, the salience the pandemic has given this issue means we now have an unparalleled opportunity to get better at anticipating and preventing project overruns using advanced forecasting and risk management techniques.”

Researchers also used nPlan’s dataset to discover the specific activities within schedules that are most likely to cause delays, finding that 45% of activities related to structural steel end up taking longer than planned. This finding is likely to cause further concern among contractors already struggling with steel shortages and delayed deliveries of steel.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Longer reads
Down and changing: ICm20 crane maker ranking
A decline in 2025 but perhaps smaller than might have been expected
Seven construction technology trends for 2026
Experts say mixed-fleet data, real-time intelligence and autonomous machines will reshape project planning and field execution
Electrifying change
Can there be a pain-free approach to powering the next generation of construction equipment?
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Electrifying change

NEW ARTICLE

Off-Highway Research highlights steady progress in electrification, with market penetration at 0.8% and forecast to more than triple to over 3% by 2028. Nate Keller of Moog shares how hybrid innovation could accelerate this shift in the decade ahead.

Read now