Analysis | The 5 big risks facing contractors on nuclear builds

Premium Content
The Sarens blue and yellow super heavy lift ring crane type SGC-250 The SGC-250, nicknamed Big Carl, at work on the Hinkley Point C nuclear power station construction project in the UK.

The next wave of nuclear construction promises years of work for contractors.

But it also presents significant risks, mainly in the form of time and cost overruns.

Interest in large conventional reactors and small modular reactors (SMRs) is gathering pace, with North America and Europe looking to rebuild capabilities eroded by decades of limited new construction.

For Mark Falloon, US engineering & construction leader at Marsh, the global insurance broker and risk adviser, the opportunity demands a realistic assessment of what contractors can control. Before joining Marsh, Falloon spent 17 years at Bechtel, including four as global head of risk management. An accountant by background, he has worked in risk and insurance for more than 30 years.

Speaking to Construction Briefing following Marsh’s webinar, “Addressing Construction Contractor Risks and Considerations on Nuclear Projects”, Falloon expanded on five central risks. And he explained why building more reactors could ease some of them without making others disappear.

1) Getting to grips with new technology

Small modular reactors (SMRs) promise abundant power for electricity-hungry data centres and as a result, multiple different developers are all in the throes of trying to get their reactors off the ground. But the learning process is only beginning for those many competing designs.

Portrait image of Mark Falloon Mark Falloon

The smaller size of SMRs compared to conventional nuclear plants does not remove the difficulty of building first-of-a-kind (FOAK) and early-of-a-kind (EOAK) technologies, even if in principle SMRs should eventually prove faster and cheaper to build.

“I think the idea is that the capital investment is not as big, the land requirement is not as much, but certainly it’s going to take time to get familiar and to build them,” Falloon says.

Until that happens, the new technology posts an inherent risk in terms of time and cost overruns. That means the benefits promised for a mature SMR programme should not be assumed for its first projects, although repeat construction should eventually offer a route better performance.

Familiar designs allow contractors to apply lessons from earlier projects, reducing uncertainty over sequencing, costs and schedules. “With anything, the more you do it the better you get at it,” says Falloon.

The benefit of repeatability is already starting to be seen on larger nuclear plants. For example, while Hinkley Point C in the UK is running several years behind schedule and is billions of pounds over its original budget, energy company EDF is promising programme efficiencies and cost savings for Sizewell C, which will be based on the same reactor design as Hinkley Point C. By replicating the design, there are expected to be just 60 changes at Sizewell C, compared to 7,000 at Hinkley Point C.

2) Supply chain constraints

In the webinar, Falloon highlighted the limited pool of suppliers able to meet nuclear requirements, alongside the engineering and manufacturing demands of new technologies. These constraints create exposure to delays beyond the contractor’s immediate control.

The small, tight market for components required in nuclear plants requires products to be certified by regulators (the Nuclear Regulatory Commission in the case of the US), and original engineering and manufacturing.

“Certainly supply chain is going to be a big issue as far as being able to get the necessary materials and parts that are going to be required for these reactors,” he says.

Repeat orders could help suppliers develop capacity and experience. But a growing project pipeline also means greater demand on that capacity.

For contractors, the availability of specialist components therefore needs to inform the programme from the outset, rather than becoming a procurement problem after a completion date has been promised.

3) Workforce gaps

The industry also has to replace experience that is leaving it.

“The workforce that has worked on nuclear is certainly aging out,” says Falloon.

After long gaps between new builds, the challenge extends beyond recruiting enough people. Workers need the skills to meet nuclear construction requirements, while utilities need engineers and operators who can run the completed plants.

Falloon says utilities and technology providers must invest in the next generation. He points to contractors already working with unions, trade schools and people leaving the military to train recruits for construction and operational roles.

This is another area where repetition could improve delivery, provided experienced teams can pass their knowledge on. A pipeline of projects offers the opportunity to rebuild that expertise, but training has to begin before workforce shortages becomes a constraint on sites.

4) Design coordination and constructability

Falloon’s webinar highlighted the coordination required between original equipment manufacturers (OEMs) and contractors, including exacting specifications and detailed quality records. Design changes and regulatory requirements can complicate that relationship further.

He recalled a project where redundant safety-system cabling shared a tray with primary cabling. The regulator rejected the arrangement, triggering substantial rework.

The example illustrates how an installation decision can undermine an otherwise advancing programme. “You’re working to a design and you get to a certain point and then regulators come in, do a safety check and say, ‘Okay, well, that’s, that’s not right. You need to redo, it’. And so all of a sudden, you were at 40% complete and now you have to redo, rip it out, and you’re back to 20% complete,” he says.

For contractors, close coordination with technology providers and a clear understanding of regulatory expectations are therefore fundamental to planning. Falloon also argues that changing requirements complicate any attempt for contractors to be able to promise a fixed price.

5) Contractual allocation of risk

The final risk brings the other four together: who pays when things go wrong?

Falloon believes there are contractors with the experience to deliver the anticipated work. But he is less convinced they will accept the commercial terms some owners might want.

“Contractors just can’t handle taking a fixed price job, especially based on the history that we’ve seen in the last 20 years,” he says (referring to significant time and cost overruns on nuclear projects built over that period). “I don’t think any contractor is going to take these jobs on a lump sum, fixed price basis,” he says.

Instead, he anticipates cost-reimbursable or target-price arrangements, with risks divided according to what the contractor, owner and technology provider can control.

That requires a relationship capable of resolving problems without immediately becoming adversarial. “It has to be a win-win. It can’t be a win-lose,” he says.

And he suggests that nuclear construction can become more predictable as designs, suppliers and workforces gain experience. But those improvements will take successive projects to achieve. Contracts for the first wave at least must reflect the industry’s capabilities and leave contractors financially able to deliver the next one.

Longer reads
How is Terex’s sale of Genie progressing?
Simon Meester, CEO of Terex, provides updates on the work to seperate Genie and its search for a buyer during Q3 earnings call 
Kobelco’s three objectives after buying 70% of CNH’s construction machinery arm
Japanese construction equipment manufacturer Kobelco has set out three objectives at the heart of its move to buy 70% of CNH Industrial’s construction machinery business
Different approaches to cranes and lifting for data centre construction
Prolific data centre construction is seeing different approaches to lifting
CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
Peter Collinson VP Sales – Construction Division Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA